As drivers are warned
of I-405 closures starting Saturday in preparation for Carmageddon II, they are
also learning the full Sepulveda Pass Improvements Project is running about
four to six months behind schedule. At a community meeting Thursday night in
the Skirball Cultural Center, project manager Michael Barbour said crews have
encountered delays in getting the Mulholland Bridge ready for the full freeway
closure Sept. 29 to Sept. 30.
But in preparation for
the second phase of the Mulholland Bridge demolition and reconstruction, drivers
should expect early 405 full closures of the northbound and southbound lanes to
take place this weekend and next weekend leading up to Carmageddon II when both
sides of the freeway will be shut down...
============================
Carmageddon II impact on drivers:
-From Sept. 8 to Sept.
9, there's a full southbound directional closure from the U.S. 101 to the Getty
Center ramps from 11 p.m. to 9 a.m.
-From Sept. 15 to Sept.
16, there's a full northbound directional closure from the Getty Center ramps
to the U.S. 101 from 11 p.m. to 9 a.m. The Mulholland Bridge will also close
from that Friday at 10 p.m. to Sunday at 8 a.m. that weekend for roadway
alignment and elevation adjustment.
-From Sept. 21 through
Sept. 24, there will be a Mulholland Bridge traffic switch, roadway alignment
and elevation adjustment. Mulholland Drive closes from that Friday at 10 p.m.
to Monday at 6 a.m.
Ramps will begin
closing as early as 7 p.m. on Friday, Sept. 28, within the freeway closure
limits. Lanes will begin closing as early as 10 p.m. on Friday.
-Full closure of the
I-405 begins Saturday at 12:01 a.m. The northbound I-405 is closed from the
I-10 to U.S. 101. The southbound I-405 is closed from the U.S. 101 to the Getty
Center Drive ramps. The Mulholland Bridge and Haskell ramps close, as well as
northbound U.S. 101 connectors from the I-405.
-The I-405 is scheduled
to reopen Monday, Oct. 1, at 5 a.m…
No comments: