From Metro:
Driveway Installation at UCLA Lot 36 and Veteran Ave.
- Metro contractors are continuing preconstruction activities at UCLA Lot 36 for Section 3 of the Purple (D Line) Extension. Work includes potholing, sound wall installation, fence removal, tree removal, banner placement, and driveway installation. Work will be ongoing through June 2021.
- Driveway installation on Veteran Ave is scheduled for June 2 to 7.
- South sound wall installation is scheduled for June 14 to 18.
- Work hours: Monday to Friday, from 9 am to 3:30 pm
---
Traffic Control:
- Intermittent lane reduction on westbound Wilshire Blvd between Gayley Ave and Veteran Ave.
- Intermittent sidewalk closures on Veteran Ave and Wilshire Blvd adjacent to UCLA Lot 36.
- Intermittent lane reduction on northbound Veteran Ave between Wilshire Blvd and Kinross Ave.
---
Noteworthy
- All work has received the necessary permits and approvals.
- Access to driveways, residences & businesses will be maintained at all times unless notified in advance.
- Access for pedestrians will be maintained outside of construction zones.
- Access for the Fire Department and emergency responders will be maintained.
- Parking restrictions will be implemented in the immediate area of the work zone.
- For construction-related issues needing immediate attention, please call Metro’s 24-hour Hotline at 213.922.6934.
---
Metro Access
- During construction, some Metro bus lines could be affected, and some bus stops might be relocated.
- For information on changes to Metro service, please call 323.GoMetro or visit: https://www.metro.net/service/advisories/
No comments:
Post a Comment